《工程(英文)》 >> 2018年 第4卷 第1期 doi: 10.1016/j.eng.2017.07.001

超特长隧洞TBM 集群施工风险管控技术

Xinjiang Association for Science and Technology, Urumqi 830011, China

收稿日期: 2017-05-24 修回日期: 2017-06-24 录用日期: 2017-07-14 发布日期: 2018-02-23

下一篇 上一篇

摘要

北疆供水二期工程,总长540 km。其中,隧洞总长516 km,加上49 条各种缓斜井和竖井,隧洞掘进总进尺569 km。特别是喀—双隧洞单洞长283 km,是目前世界最长的输水隧洞。主洞划分了18 台隧洞掘进机(TBM)掘进段和34 个钻爆法施工段,施工掌子面多达91 个。该工程不仅对建设管理、风险防控、安全高效施工提出前所未有的挑战,同时也对TBM 及其配套设备的设计、制造、运维提出了更高的要求。有必要根据工程特点和不良地质条件,分析工程建设面临的重大难题和关键技术,系统查找风险源、合理划分风险等级、明确责任主体、建立分级管控机制。本文提出了应用超前地质预报技术、岩机信息感知和融合的智能掘进技术、监测预警及现代信息技术,用以科学指导风险管控,提高安全掘进效率的技术思路。

图片

图1

图2

图3

图4

图5

图6

图7

图8

参考文献

[ 1 ] Zheng YL, Zhang QB, Zhao J. Challenges and opportunities of using tunnel boring machines in mining. Tunn Undergr Space Technol 2016;57:287–99. 链接1

[ 2 ] Liu Q, Huang X, Gong Q, Du L, Pan Y, Liu J. Application and development of hard rock TBM and its prospect in China. Tunn Undergr Space Technol 2016;57:33–46. 链接1

[ 3 ] Zhang J. Application of TBM in water diverting project from Yellow River at Wanjiazhai, Shanxi. Construct Mach 2003;2:32–3. Chinese.

[ 4 ] Deng M. Key techniques for group construction of deep-buried and super-long water transfer tunnel by TBM. Chin J Geotech Eng 2016;38(4):577–87. Chinese. 122 链接1

[ 5 ] Wang MS, Wang ZS. Construction technology of TBM driving across fracture zone. Tunn Construct 2001;21(3):1–4. Chinese.

[ 6 ] Du Y, Xu X, Zhi X. Full-face rock tunnel boring machine: TBM maintenance and monitoring. Wuhan: Huazhong University of Science and Technology Press; 2013. Chinese.

[ 7 ] Zhao Y, Jiang H. Present situation analysis and new development of tunnel advance forecast technology. Highway Tunn 2010;1:1–7. Chinese.

[ 8 ] Jie S. The three-dimensional seismic ahead prospecting method and its application for adverse geology in tunnel construction [dissertation]. Jinan: Shandong University; 2016. Chinese.

[ 9 ] Li SC, Nie LC, Liu B, Tian MZ, Wang CW, Song J, et al. Advanced detection and physical model test based on multi-electrode sources array resistivity method in tunnel. Chin J Geophys 2015;58(4):1434–46. Chinese.

[10] Li C, Gu T, Liao Y, Ding J. Discussion on TBM construction through faults, karst, groundwater and other poor geological sections. J Eng Geology 2011;19 (Suppl):396–401. Chinese.

[11] He F, Guo R, Li S, Lin Y, Ran M, Shan Z. Prediction of water gushing in front of pile surface by rock mass temperature tunnel. Chengdu: Southwest Jiaotong University Press; 2009. Chinese.

[12] Zhu G, Qian G, Zhang C. Simulation of DC focusing electric field in tunnel based on APDL. J Huazhong Univ Sci Technol 2015;43(12):52–5. Chinese.

[13] Liu Q, Liu J, Pan Y, Kong X, Cui X, Huang S, et al. Research advances of tunnel boring machine performance prediction models for hard rock. Chin J Rock Mech Eng 2016;35(S1):2766–86. Chinese.

[14] Tan Q, Sun X, Xia Y, Cai X, Zhu Z, Zhang J, et al. A wear prediction model of disc cutter for TBM. J Cent South Univ 2017;48(1):54–60. Chinese.

相关研究