Abstract

Highway multi-arch tunnel as a new structure form has been developed in resent decades with the rapid development of high level road, and this tunnel structure form has the merits of good adaptability and superiority in the condition of complex land form and difficult line designation. However, compared with individual tunnel and conjoined tunnel,multi-arch tunnel has the question of mother rock's frequent perturbation, construction difficulty, et al. In the geological condition of shallow buried, soft rock, and carst, et al. the mother rock of these kinds of tunnel must be paid attention in the whole construction stage. This paper, taking the Baiguoba Tunnel, Enshi to Lichuan section, Hurongxi express way, as the background and combining field engineering construction, analyzed the Baiguoba Tunnel with MIDAS-GTS, laid the emphasis on surrounding rock mechanics property, drew a conclusion of stress regularity, and put up the countermeasure to the weak part.

Figures

图1

图2

图3

图4

图5

图6

图7

图8

图9

图10

图11

图12

图13

References

[ 1 ] 景志富,孙 波.大跨度双跨联拱隧道的新奥法 施工 [ J] .铁道 工程学报,2002 ,( 1 ) :62 -65 link1

[ 2 ] 潘昌实.隧道力学数值方法[ M] .北京:中国铁道出版社,1995

[ 3 ] 陈秋南,赵明华,张永兴,等.偏压双连拱隧道信息化施工与仿真分析[J].岩石力学与工程学报,2006,(8):1723-1727 link1

[ 4 ] 蒋树屏,刘洪洲,鲜学福.大跨度扁坦隧道动态施工的相似模拟与数值分析研究[J].岩石力学与工程学报,2000,19(5):567-572 link1