The lowering as a whole technology of Sutong Bridge 5 800 t weigh steel cofferdam

1. Jiangsu Provincial Sutong Bridge Construction Commanding Department, Nanjing 210006, China;

2. School of Civil Engineering and Mechanics of HUST, Wuhan 430074, China

Received: 2009-06-07 Available online: 2010-02-03 10:00:18.000

Next Previous

Abstract

Sutong Bridge is the first cable stayed bridge with the span exceeds 1 000 m which located in the mouth of Yangtze River. Its pylon foundation located in the river where the water is deep and current speed is high, and adopted the bored group piles foundation which is the largest group piles foundation. To the group piles foundation with the construction condition of deep water and high speed current, the exactly construction of the steel cofferdam which provided dry condition for the pile caps construction is a problem. This paper discussed the lowering as a whole technology of Sutong Bridge 5 800 t weigh steel cofferdam from 6 respects such as selection of lowering scheme, design, fabrication, lowering techniques, synchronousness controlling and orientation. In which, the design combined the coping of bored piles construction platform with bottom of steel cofferdam, the lowering as a whole techniques, synchronousness controlling and orientation technology are innovation.

Figures

图1

图2

图3

图4

图5

图6

References

[ 1 ] 毕见山,王慧东.扬中夹江二桥桩基础承台钢吊箱施工技术[J].国防交通工程与技术,2005,(3):43-45 link1

[ 2 ] 余峰.武汉白沙洲大桥#3主墩大型钢吊箱施工[J].水运工程,2000,(3):56-59 link1

[ 3 ] 刘金平.武汉白沙洲大桥特大型钢吊箱施工测量[J].河港工程,1998,(1):21-27

[ 4 ] 陈光福.特大桥水下桩基承台施工技术[J].河港工程,2002,(2):1-14

[ 5 ] 胡益康,丘斌.珠江特大桥吊箱围堰设计与施工[J].企业技术开发,2004,(6):21-23 link1

[ 6 ] 罗瑞华.芜湖长江大桥主塔墩大直径双壁钢围堰深水基础施工[J].公路,2003,(4):44-46 link1

[ 7 ] 胡安祥.肇庆大桥承台钢吊箱的设计与施工[J].河港工程,2000,(3):6-14

[ 8 ] 李景龙,欧阳衡.主墩承台采用无底吊箱围堰施工工艺[J].水运工程,2004,(6):75-76 link1

[ 9 ] 王晔.深水大桥钢吊箱围堰施工技术[J].科技情报开发与科技,1999,(3):52-53 link1

Related Research