Xihoumen Bridge is the longest two-span continuous steel box girder suspension bridge in China. Several problems have been encountered due to severe natural environment during the erection of steel box girder at anchor-side of north side span of the bridge. The key technique and construction process of erection and linetype adjustment for the steel box girder are introduced.
Keywords
suspension bridge ; steel box-girder ; Xihoumen Bridge ; anchor-side of north side span ; erection and adjustment of linetype ; key technique
References
[ 1 ] 钱冬生,陈仁福.大跨悬索桥的设计与施工(修订版)[M].成都:西南交通大学出版社,1999
[ 2 ] 牛和恩.虎门大桥工程第二册·悬索桥[M].北京:人民交通出版社,1988
[ 3 ] 潘世建,杨盛福.东航道悬索桥·海沧大桥建设技术第四册[M].北京:人民交通出版社,2001
[ 4 ] 吴胜东.润扬长江公路大桥建设第三册·悬索桥[M].北京:人民交通出版社,2005
[ 5 ] NielsJ.Gimsing编,西南交大土木学院桥梁系与中铁大桥局桥研院译,钱东生校.大贝耳特海峡:东桥[M].成都:西南交通大学出版社,2008
[ 6 ] 卢伟,邓亨长,龙勇,等.西堠门大桥钢箱梁安装[J].公路,2009,1:59-65 link1
[ 7 ] 唐茂林,许宏亮,沈锐利,等.西堠门大桥无索区梁段线形调整与控制[J].公路,2009,1:43-47 link1