Abstract
Based on the introduction of building launching shaft and the shield launching of Beijing Rail Transit which constructed with a slurry shield machine by Ø12.04 m, some key technologies of shield launching were summarized in the urban areas and the water-rich grit stone geological conditions.
Keywords
urban ; water-rich sandy gravel ; big diameter ; slurry shield ; launching