Abstract

The construction of Three Gorges Project (TGP) is characterized by large construction scale, high construction intensity and complexity in technology. In view of various technical difficulties such as navigation in construction period,Changjiang river closures, high intensity concrete and earth rock construction,roller compacted concrete (RCC) cofferdam in 3-stage III and double line five step ship lock,the general arrangement of the project construction is as follows:construction in 3-stage,navigation with diversion channel and power generation under cofferdam project.The practice and innovation achievements in river diversion during construction as well as earth rock and concrete construction were presented emphatically.

References

[ 1 ] 长江水利委员会长江勘测 规划设 计研 究 院.三 峡 工 程 设 计 论 文集[ M] .北京:中国水利水电出版社,2003.

[ 2 ] 郑守仁.三峡大坝混凝土设计及温控防裂技术突破[ J] .水利 水电科技进展,2009 , 29 ( 5 ) :46 -53. link1

[ 3 ] 谢修发,陈文斌.三峡工程施 工准 备 及 设 施 设 计 与 实 施 [ M] . 武汉: 长江出版社,2007.

[ 4 ] 翁永红,谢 红 忠,夏 仲 平.混 凝 土 坝 施 工 实 时 动 态 仿 真 [ M] . 北京: 中国电力出版社,2003.

Related Research