Whole construction process real-time schedule control and visual analysis of the long distance diversion tunnel based on simulation

 

1.State Key Laboratory of Hydraulic Engineering Simulation and Safety, Tianjin University, Tianjin 300072, China;

2.Ertan Hydropower Development Company,Chengdu 610021, China

Funding project:国家自然科学基金(90815019);国家自然科学基金创新研究群体科学基金(51021004);“十二五”国家科技支撑计划(2011BAB10B06) Received: 2011-09-16 Available online: 2011-12-13 11:19:30.000

Next Previous

Abstract

Long diversion tunnel is often featured by great embedded depth, long tunnel line, large hole diameter and extremely complicated geologic conditions. The engineering quantity of each process is large, and the influence is enormous; therefore, the internal and external environment and constraint condition are changed in the actual construction, leading to the deviation between formerly construction schedule plan and actual construction schedule plan. If the deviation isn't corrected timely, the formerly plan can not guide the actual construction. In this paper, using computer simulation technology, control theory and virtual reality technology, the whole construction process real-time schedule control and visual analysis of the long distance diversion tunnel based on simulation are proposed. The feasibility study and scientific basis is provided for the real-time control of construction schedule.

Figures

图1

图2

图3

图4

图5

图6

图7

图8

图9

References

[ 1 ] 钟登华,李景茹,刘奎建.全过程动态仿真技术及其在大型工程施工管理中的应用[J].天津大学学报,2003,36(3):347-352. link1

[ 2 ] 康凤举.现代仿真技术与应用[M].北京:国防工业出版社,2001.

[ 3 ] 温家林.网络计划软件编制及其在施工仿真中的应用[D].天津:天津大学,2008. link1

[ 4 ] 刘奎建.大型地下洞室群施工进度实时控制研究[D].天津:天津大学,2007. link1

[ 5 ] 李景茹,钟登华,刘东海,等.水利水电工程三维动态可视化仿真技术与应用[J].系统仿真学报,2006,18(1):116-119. link1

[ 6 ] 王帅.鲁地拉地下洞室群施工动态可视化仿真与优化研究[D].天津:天津大学,2007. link1

[ 7 ] 钟登华,刘奎建.基于实时仿真的地下洞室群施工进度预测与控制[J].天津大学学报,2007,40(6):721-725. link1

[ 8 ] Falco M D, Macchiaroli.Timing of control activities in project planning[ J] .International Journal of Project Management.1998 , 16 ( 1 ) : 51 -58. link1

[ 9 ] 吴世勇,王鸽.锦屏二级水电站深埋长隧洞群的建设和工程中的挑战性问题[J].岩土力学与工程学报,2010,29(11):2161-2171. link1

[10] Carr Robert I.Cost, schedule and time variances and integration [ J] .Journal of Construction Engineering and Management, 1993 ( 6 ) : 245 -265. link1

[11] Simaan Abourizk, Yasser Mohamed.Optimal construction project planning[ C] //Proceedings of the 2002 Winter Simulation Con- ference( 0780376145 ) .San Diego: IEEE, 2002 : 1704 -1708.

Related Research