A Multi-objective Optimization Decision-making Model for Project Time - resource Tradeoff Problem

1. Institute of Systems Engineering, Wuhan University, Wuhan 430072, China

2. School of Mathematics and Statistics, Wuhan University, Wuhan 430072, China

Funding project:国家自然科学基金资助项目(60274048, 70371032) Received: 2004-03-17 Revised: 2004-04-28 Available online: 2005-02-20

Next Previous

Abstract

In the project scheduling and management, the time-resource tradeoff problem is to seek the objective of minimizing the project duration and the total consumed-resources cost under the requirement of the absolute due date of project, and determine an efficient project scheduling according to some precedence relationship and the renewable resource constraints. A new multi-objective optimization decision-making model with time-resource tradeoff problem is proposed, in which objective functions with conflict one another are defined as adaptive and adjustable between the project duration and the total consumed-resources cost in all period. A satisfied feasible solution can be obtained in the solution procedure by compromising and adjusting relationship between the project duration and the total consumed-resource cost. A numerical example is illustrated. In addition, some characteristics on this two-player game are given in the corresponding Lagrangian relaxation form associated with the resource constraints.

Figures

图1

References

[ 1 ] Herroelen W, Demeulemeester E, Reyck B D. A classification scheme for project scheduling [A]. Weglarz J. Project Scheduling Recent Models, Algorithms and Applications [M]. Kluwer Academic Publishers, 1999. 1~26

[ 2 ] LeuSS , ChenAT , YangCH .AGA basedfuzzyoptimalmodelforconstructiontime costtrade off[J].InternationalJournalofProjectManagement, 2001, 19:47~58

[ 3 ] LiH , CaoJN , LoveP .UsingmachinelearningandGAtosolvetime costtrade offproblems[J].JournalofConstructionEngineeringandManagement, 1999, 125 (5) :347~353 link1

[ 4 ] SiminP , HornSJ .Time resourcetradeoffproblem[J].IEEETransactionsonEngineeringManagement, 1996, 43 (4) :411~417

[ 5 ] GolenkoGinzburgD , GonikA .Aheuristicfornetwork projectschedulingwithrandomactivitydurationsdependingontheresourceallocation[J].InternationalJournalofProductionEconomics, 1998, 55:149~162

[ 6 ] DeckroRF , HebertJE .Amultipleobjectiveprogrammingframeworkfortrade offsin projectscheduling[J].EngineeringCostsandProductionEconomics, 1990, 18:255~264

[ 7 ] BruckerP , DrexlA , M hringRM , NeumannK , PeschE .Resource constrained projectscheduling:Notation, classification, models, andmethods[J].EuropeanJournalofOperationalResearch, 1999, 112:3~41

[ 8 ] Icmeli O, Erenguc S S. The resource constrained time/cost tradeoff project scheduling problem with discounted cash flows [J]. Journal of Operations Management, 1996, 14: 255~275

[ 9 ] NeumannK , ZimmermannJ .Resourcelevelingforprojectswithschedule dependenttimewindows[J].EuropeanJournalofOperationalResearch, 1999, 117:591~605

[10] Neumann K, Zimmermann J. Procedures for resource leveling and net present value problems in project scheduling with general temporal and resource constraints [J]. European Journal of Operational Research, 2000, 127: 425~443

[11] ChristofidesN , AlvarezValdesR , TamaritJM .Projectschedulingwithresourceconstraints:abranchandboundapproach[J ].EuropeanJournalofOperationalResearch, 1987, 29:262~273

[12] LeuSS , YangCH .A genetic algorithm basedresource constrainedconstructionschedulingsystem[J].ConstructionManagementandEconomics, 1999, 17:767~776