Journal Home Online First Current Issue Archive For Authors Journal Information 中文版

Strategic Study of CAE >> 2006, Volume 8, Issue 6

Numerical Simulation of Contact Stresses under North Anchor Foundation of Runyang Suspension Bridge

Department of Engineering Mechanics, Hohai University, Nanjing 210098, China

Received: 2004-10-29 Revised: 2006-02-13 Available online: 2006-06-20

Next Previous

Abstract

For the concreting construction and running process of north anchor foundation of Runyang suspension bridge, the three - dimension finite element simulation model considering the interaction of anchor foundation and soil is founded based on the secondary development of Marc. During the construction process, the change of groundwater level results in the change of the water pressure under foundation, and then the change of the distribution of contact stresses. By the numerical simulation from the construction to running process, the change law of the contact stresses of gravitational rock - socketed anchor foundation is opened out. By the computation for the engineering example, during different stages of concreting construction, though the contact stresses of different parts of anchor foundation take on different characters,the contact stresses of north anchor foundation from the concreting process to running process satisfy the request of design as a whole.

Figures

图1

图10

图11

图2

图3

图4

图5

图6

图7

图8

图9

References

[ 1 ] 吴胜东, 吉林, 阮静.润扬大桥悬索桥北锚碇基础方案比选[J].桥梁建设, 2003, (2) :44~46 link1

[ 2 ] 彭德运.大跨悬索桥锚碇基础的设计与施工[J].铁道标准设计, 2003, (1) :19~23 link1

[ 3 ] 张杰, 钱冬生.大跨悬索桥塔和锚碇的合理设计[J].桥梁建设, 2000, (4) :20~22 link1

[ 4 ] 钱冬生, 陈仁福.大跨悬索桥的设计与施工[M].西安:西南交通大学出版社, 1999 link1

[ 5 ] 陈志坚, 游庆仲, 等.振弦式压力盒在刚性接触面应力监测中的应用研究[J].中国工程科学, 2002, 4 (12) :80~85 link1

[ 6 ] 冯兆祥, 吉林, 钟建弛.江阴大桥锚碇基础接触应力的实测研究[J].公路, 2003, (2) :23~25 link1