Research of water distribution of tunnel lining in Karst region

1. School of Civil Engineering and Architecture, Beijing Jiaotong University, Beijing 100044, China;

2. Yichang -Wanzhou Railway Construction Headquarters of Ministry of Railways, Enshi, Hubei 445000, China

Funding project:铁道部计划项目(2004G033);国家自然基金资助项目(50878019) Received: 2009-10-30 Available online: 2009-12-15 09:19:14.000

Next Previous

Abstract

Tunnel lining water pressure problem has been bone of contention for a long time. Relying on Yichang-Wanzhou Railway karst tunnels to research on distribution of linning water pressure on different anti-drainage patterns (the whole block, block combined with drainage and drainage mode). The primary research method was model test and field monitoring. Model test scale was 1∶16, and test apparatus could be applied earth pressure and water pressure. Acquiring the distribution of linning water pressure by model test: the lining water pressure can't discounted and reduced by the grouting ring at the condition of whole block; the lining water pressure reduced significantly and linear decreased as the development of drainage discharge at the condition of block combined with drainage, simultaneously, the better the effect of grouting, the more outstanding the water pressure reduce; the lining still bear a certain degree of water pressure at the condition of drainage. A part of conclusion about distribution of linning water pressure from model test has been verified in field monitoring.

Figures

图1

图2

图3

图4

图5

图6

图7

图8

图9

图10

图11

图12

图13

图14

图15

图16

图17

References

[ 1 ] 高新强,仇文革.隧道衬砌外水压力计算方法研究现状与进展[J].铁道工程学报,2004,4(84):128-132 link1

[ 2 ] 王秀英,谭忠盛,王梦恕,等.高水位隧道堵水限排围岩与支护相互作用分析[J].岩土力学,2008,29(6):1623-1628 link1

[ 3 ] 高新强.高水压山岭隧道衬砌水压力分布规律研究[D].成都:西南交通大学,2005 link1

[ 4 ] Wang Xiuying, Tan Zhongsheng, Wang Mengshu, et al.Theoretical and experimental study of external water pressure on tunnel lining in controlled drainage under high water level [ J] .Tunnelling and Underground Space Technology,2008 ,23 ( 9 ) : 552 -560 link1

[ 5 ] 王建宇.隧道围岩渗流和衬砌水压力荷载[J].铁道建筑技术,2008,(2):1-6 link1

[ 6 ] 蒋忠信.隧道工程与水环境的相互作用[J].岩石力学与工程学报,2005,24(1):121-127 link1

[ 7 ] 张祉道.隧道涌水量及水压计算公式半理论推导及防排水应用建议[J].现代隧道技术,2006,43(1):1-7 link1

[ 8 ] 张民庆,黄鸿健,苗德海,等.岩溶隧道水压力的研究与确定[J].铁道工程学报,2008,5(116):53-58 link1

[ 9 ] 吉小明,白世伟,杨春和.岩体地下流固耦合理论的研究综述[J].岩石力学与工程学报,2001,20(增1):846-849

[10] 莫阳春,周晓军.岩溶隧道施工围岩变形动态监测与仿真分析[J].岩石力学与工程学报,2008,27(增2):3816-3821 link1