Abstract

Through introducing the construction method of negative ring demolition during transforming cutter head and replacement technique of Beijing Rail Transit Line 2 bid section in detail, the experience of negative ring demolition and replacement techniques of large diameter slurry shield were summarized, which would provide reference to the implementation of the construction scheme.

Figures

图1

图2

图3

图4

图5

图6

图7

图8

图9

图10

References

[ 1 ] 刘建航,侯学渊.盾构法隧道[M].北京:中国铁道出版社,1991.

[ 2 ] 周文波.盾构法隧道施工技术及应用[M].北京:中国建筑工业出版社,2004.

[ 3 ] 张凤祥,付德明,杨国祥.盾构隧道施工手册[M].北京:人民交通出版社,2005.

[ 4 ] 陈馈,洪开荣,吴学松.盾构施工技术[M].北京:人民交通出版社,2009.

[ 5 ] 钢结构设计手册编辑委员会.钢结构设计手册[M].北京:中国建筑工业出版社,2004.

Related Research