Technology of freezing reinforcement and risk control at all direction in construction of break in and break out of shield

Shanghai Branch,China Coal No.5 Construction Co., Ltd., Shanghai 201900, China

Received: 2011-08-24 Available online: 2012-04-17 16:17:37.000

Next Previous

Abstract

The construction of break-in and break-out of shield in the complicated condition of aquiferous geology, by the method of horizontal freezing, is to extend or deepen the frozen thickness outside the horizontal freezing ring which encircle the shield at all directions and prevent from water leaking and sand pouring effectively. The problem of long-distance drilling in the finished end well is solved easily by a longdistance horizontal drilling and anti-extrusion connector. It has proved that the technology of freezing reinforcement and risk control at all direction, in the construction of break-in and break-out of shield in the complicated condition of aquiferous geology is reliable, easy and will have great value to be spread in the risk control of construction of break-in and break-out.

Figures

图1

图2

图3

图4

图5

图6

图7

图8

References

[ 1 ] 吉田辉,上本胜广,吉川正.冻着强度试验方法[C].地盘工学研究发布会发表讲演集,2003:339-340.

[ 2 ] 中国矿业大学,同济大学,北京中煤矿山工程有限公司,等.上海地区人工冻土热物理参数试验研究报告[R],2008.

[ 3 ] 上海市建设和交通委员会.DC/TJ08-902-2006上海市工程建设规范旁通道冻结法技术规程。

[ 4 ] 推云龙,等.简明建井工程手册[M].北京:媒炭工业出版社,2000.