Research on simulation evaluation method based on duration contro-llability of network schedule

State Key Laboratory of Hydraulic Engineering Simulation and Safety, Tianjin University, Tianjin 300072, China

Received: 2013-01-23 Available online: 2015-01-13 10:49:42.000

Next Previous

Abstract

As the fact that schedulers usually utilizing resources re-allocation and improving resource-utilization efficiency in coping with project delay caused by risk events,a stochastic simulation evaluation method based on duration controllability of network schedule was put forward. This method took the resource allocation and utilization of margin of the activity as controllable indicators, and considered different constructability of measures reaction to different occur time of risk events. Through the stochastic simulation of each risk events occur time, delay of activity duration and effect of the risk reaction,the distribution of project duration was simulated which was utilized to evaluate the rationality of the network schedule. A case indicates that,compared with traditional simulation evaluation methods such as duration-based and factors-based Monte-Carlo simulation, simulation results of the duration controllability-based is more reasonable.

Figures

图1

图2

图3

图4

图5

图6

图7

图8

References

[ 1 ] 李万庆. 工程网络计划技术 [M]. 北京:科学出版社,2009.

[ 2 ] Elmaghraby S E. Activity Networks:Project Planning and Control by Network Models [M]. New York:John Wiley and Sons, 1977.

[ 3 ] Wolfgang Tysiak. Risk Management in projects:The monte carlo approach versus PERT [C]// The 6th IEEE International Conference on Intelligent Data Acquisition and Advanced Computing Systems:Technology and Applications. 2011:906-910. link1

[ 4 ] 李若刚,王国祥,李 跃,等. 关于网络计划模型中的时间不确 定性的讨论[J]. 系统工程与电子技术,1997,19(8):40-45. link1

[ 5 ] Bonny J B,Frein J P. Handbook of Construction Management and Organization [M]. New York:Van Nostrand Reinhold Company,1973.

[ 6 ] Newbold R C. Project Management in the Fast Lane-applying the Theory of Constraints [M]. Boca Raton:St. Lucie Press,1998.

[ 7 ] Alan R Bowman. Developing activity duration specification limits for elective project control [J]. European Journal of Operational Research,2006,174:1191-1204. link1

[ 8 ] Cyril Briand,Jean-Charles Billaut. Cooperative project scheduling with controllable processing times:A game theory framework [C]// IEEE 16th Conference on Emerging Technologies & Factory Automation,2011. link1

[ 9 ] Van Slyke R M. Monte Carlo methods and the PERT problem [J]. Operation Research,1963,11:839-860. link1

[10] 褚春超. 工程项目进度管理方法与应用研究[D]. 天津:天津大 学,2007. link1

[11] 王卓甫. 工程项目管理风险及其应对[M]. 北京:中国水利水电 出版社,2005.

Related Research