Control measures of installation precision of Three Gorges Project ship lift rack and nut column

Gezhouba Group Mechanical & Electrical Construction Co., Ltd., Chengdu 610091, China

Received: 2013-06-28 Available online: 2013-09-10 13:10:01.000

Next Previous

Abstract

According to technology requirements of installation precision and characteristics of rack, nut column of Three Gorges Project ship lift, and combined with the integrated environment the installation method and installation accuracy control elements have been in detailed analysis, put forward the suitable rack, nut column installation construction process and control measures for Three Gorges Project ship lift. In engineering practice, use the test of datum point to control installation precision of the rack and nut column, put forward the method that screw of finish machining technology to cooperate with jack to readjust as reinforcement measures of installation of the rack, nut column. Thus various high precision standard technical difficulties of installation of the rack, nut column, have been solved, provides the beneficial reference for the similar engineering construction.

Figures

图1

图2

图3

图4

图5

图6

References

[ 1 ] 郑守仁. 三峡工程设计重大技术问题综述[C]//三峡工程设计论 文集. 北京:中国水利水电出版社,2003,8:3-14.

[ 2 ] 钮新强,覃利明,于庆奎. 三峡工程齿轮齿条爬升式升船机设计 [J]. 中国工程科学,2011,13(7):96-103. link1

[ 3 ] 王宗禄,李俊波,杨 红,等. 三峡升船机齿条及螺母柱安装方 案研究与实施[J]. 中华民居,2012(10):218-219. link1

Related Research