Journal Home Online First Current Issue Archive For Authors Journal Information 中文版

Strategic Study of CAE >> 2014, Volume 16, Issue 8

Feasibility Study on Design and Construction of Concrete Filled Steel Tubular Arch Bridge with a Span of 700m

1. Guangxi Zhuang Autonomous Region Transportation Department,Nanning 530012,China;

2. Guangxi Zhuang Autonomous Region Road and Bridge Engineering Company,Nanning 530011,China;

3. Sichuan Provincial Transport Department Highway Planning,Survey,Design and Research Institute,Chengdu 610041,China

Received: 2014-04-27 Available online: 2014-08-13 14:20:46.000

Next Previous

Abstract

Based on the design and complete construction techniques of 500m-span concrete filled steel tubular (CFST) arch bridge, a feasibility study on design and construction techniques of 700m-span CFST arch bridge was conducted. The general design and construction schemes were figured out, and key techniques were detailed studied such as manufactory and installation of arch ribs, concrete grouting in tube, etc.. The results showed that there are no technical hurdles to build 700m-span CFST arch bridges. Considering economical efficiency, safety and other factors, CFST arch bridge is a strong competitor when building a 700m-span bridge and should be put on engineering practice and spread as soon as possible.

Figures

图1

图2

图3

图4

图5

References

[ 1 ] 郑皆连. 特大跨径RC拱桥悬拼合拢技术的探讨[J]. 中国公路 学报,1999(1):42-49. link1

[ 2 ] 郑皆连. 在劲性拱骨架上实现混凝土连续浇注的探讨[J]. 重庆 交通大学学报自然科学版,2011,30(s2):1009-1016. link1

Related Research