Due to the DOE’s decision to delay deployment of the NGNP, the licensing work has been deferred. Although numerous discussions with the NRC have occurred, and many white papers have been written on key topics, not much progress has been made in terms of resolving key issues such as containment performance requirements, source term, licensing basis event selection, and emergency planning. In cooperation with the NGNP Industry Alliance, the NGNP project submitted a proposed risk-informed licensing strategy and safety basis [
10] to the NRC for the commercial plant. The NGNP team performed a regulatory gap analysis that examined over 2500 individual regulatory requirements based on existing deterministic light water reactor criteria. The Idaho National Laboratory submitted numerous white papers to address these topics [
11−
13]. The NRC reviewed these documents [
14,
15], but has not issued formal decisions on any of the key issues affecting future designs, making it impossible to proceed with the design of the demonstration plant.