三峡升船机高精度金属结构埋件安装技术

卫书满,张为明,李辰治

中国工程科学 ›› 2013, Vol. 15 ›› Issue (9) : 87 -90.

PDF (971KB)
中国工程科学 ›› 2013, Vol. 15 ›› Issue (9) : 87 -90.

三峡升船机高精度金属结构埋件安装技术

作者信息 +

High precision installation technology of metal structure embedded parts of Three Gorges Project ship lift

Author information +
文章历史 +
PDF (993K)

摘要

针对三峡升船机工程金属结构一期及二期埋件的布置特点,并结合现场施工环境,对高精度安装作业进行了详细分析,提出了适宜三峡工程金属结构埋件安装的多种施工方案,并在三峡工程中得到广泛成功应用,解决了施工中埋件变形控制、快速高精度调整定位和高精度测量保障等技术难题,为同类工程的施工提供了借鉴。

Abstract

Based on the layout characteristics of the first-stage and second-stage metal structure embedded parts, and combined with the site construction environment, this article analyzes the high precision installation method in detail. At the same time, various construction plans which are suitable for Three Gorges Project ship lift are put forward. These construction plans which have been successfully used in Three Gorges Project have solved many technological problems, such as the deformation control of the embedded parts, fast and accurate positioning, high precision measurement and so on. Meanwhile, these technologies provide a reference for the constructions of similiar projects.

关键词

升船机 / 金属结构埋件 / 高精度 / 安装技术 / 三峡工程

Key words

ship lift / metal structure embedded parts / high precision / installation technology / Three Gorges Project

Author summay

卫书满(1972—),男,湖北大冶市人,高级工程师,主要从事水工金属结构制造安装及电站机电设备安装技术质量管理

引用本文

引用格式 ▾
卫书满,张为明,李辰治 三峡升船机高精度金属结构埋件安装技术[J]. 中国工程科学, 2013, 15(9): 87-90 DOI:

登录浏览全文

4963

注册一个新账户 忘记密码

参考文献

AI Summary AI Mindmap
PDF (971KB)

209

访问

0

被引

详细

导航
相关文章

AI思维导图

/