超大型陆上沉井封底施工技术

杜洪池,杨宁

中国工程科学 ›› 2012, Vol. 14 ›› Issue (5) : 19 -22.

PDF (1336KB)
中国工程科学 ›› 2012, Vol. 14 ›› Issue (5) : 19 -22.

超大型陆上沉井封底施工技术

    杜洪池()1、杨宁2

作者信息 +

Bottom sealing construction technology for extralarge onland caisson

    Du Hongchi1、Yang Ning2

Author information +
文章历史 +
PDF (1367K)

摘要

泰州大桥北锚碇沉井封底总方量超过30 000 m3,为目前国内立方量最大的水下封底混凝土施工工程,其施工难度大,现场组织要求高。从沉井清基、封底设备布置、封底混凝土施工工艺等方面概略介绍泰州大桥北锚碇沉井封底施工技术。

Abstract

The total quantity of concrete exceeds 30 000 m3 for the north anchor caisson of Taizhou Bridge, which is the largest quantity underwater concrete for bottom sealing construction till now in China, and its construction is quite difficult with high requirements for site organization. This article presents the bottom sealing construction technology for the caisson of north anchor of Taizhou Bridge mainly in the aspects of base cleaning, bottom sealing equipment arrangement and sealing concrete construction technique.

关键词

超大型陆上沉井基础 / 沉井封底技术 / 泰州大桥

Key words

extra large on land caisson / bottom sealilng construction technology for caisson / Taizhou Bridge

引用本文

引用格式 ▾
超大型陆上沉井封底施工技术[J]. 中国工程科学, 2012, 14(5): 19-22 DOI:

登录浏览全文

4963

注册一个新账户 忘记密码

参考文献

AI Summary AI Mindmap
PDF (1336KB)

2678

访问

0

被引

详细

导航
相关文章

AI思维导图

/