立井井塔建安工程综合施工新技术

作者信息 +

Construction technology of well shaft tower construction engineering

Author information +
文章历史 +
PDF (3792K)

摘要

以龙固煤矿1#主井提升系统施工为例,介绍了井塔建筑和井筒装备、提升机等设备安装工程平行作业的施工组织特点以及立井井塔滑模施工、井筒装备采用6层吊盘一次成井安装和永久提升机安装的施工技术,为同类型工程施工提供了一种可借鉴的综合施工应用技术。

Abstract

Taking the construction of the main shaft hoisting in Longgu 1# Coal Mine for example, the organizational characteristics of the well shaft tower and equipments, elevator and other parallel operation of installation construction were introduced, and the technologies of tower shaft slipform construction, six-disc hanging plate installation and permanent elevator installation were described. The paper can provide reference for the similar type of the construction.

关键词

平行作业 / 井塔滑模 / 井筒装备 / 提升机安装 / 施工技术

Key words

parallel operations / well tower sliding / shaft equipment / elevator installation / construction technology

Author summay

杨益明(1965—),男,江苏常州市人,工程师,主要从事煤炭建筑安装工程施工工作

引用本文

引用格式 ▾
杨益明,黄家贫,谌喜华,曹月芹,马智民 立井井塔建安工程综合施工新技术[J]. 中国工程科学, 2012, 14(2): 85-89 DOI:

登录浏览全文

4963

注册一个新账户 忘记密码

参考文献

AI Summary AI Mindmap
PDF (3704KB)

486

访问

0

被引

详细

导航
相关文章

AI思维导图

/