悬索桥施工中鞍座顶推的研究

齐东春,王昌将,沈锐利,林恰

中国工程科学 ›› 2010, Vol. 12 ›› Issue (7) : 68 -73.

PDF (723KB)
中国工程科学 ›› 2010, Vol. 12 ›› Issue (7) : 68 -73.

悬索桥施工中鞍座顶推的研究

作者信息 +

Saddle pushing analysis in suspension bridge construction

Author information +
文章历史 +
PDF (739K)

摘要

对悬索桥鞍座顶推中预偏量计算控制原则、塔顶位移与塔底应力的关系、顶推量和顶推时间的确定等几个问题进行了探讨,阐明了鞍座平衡条件的合理模式及预偏量的计算方法。结合坝陵河大桥鞍座的顶推计算分析,得出超量顶推可增加顶推时间间隔,减少顶推次数,顶推后的工况是主缆抗滑移验算的不利工况等结论。

Abstract

Some problems existing in saddle pushing, such as the pre-displacement control principle, the relation of tower top displacement and tower bottom stress, the method of determining saddle pushing stages and pushing values, are discussed. The reasonable model of saddle equilibrium condition and the pre-displacement calculation method are expounded. Combining with saddle pushing analysis of Baling River Bridge, the conclusion that the excess pushing scheme can increase the interval of each pushing and reduce pushing times is obtained. The cases following saddle pushing are the unfavorable conditions for main cables anti-sliding checking.

关键词

悬索桥 / 鞍座顶推 / 鞍座平衡条件 / 塔顶偏位 / 塔底应力

Key words

suspension bridge / saddle pushing / saddle equilibrium condition / tower top displacement / tower bottom stress

Author summay

齐东春(1978-),男,湖北宜昌市人,西南交通大学博士研究生,主要从事现代桥式及桥梁结构设计理论研究

引用本文

引用格式 ▾
齐东春,王昌将,沈锐利,林恰 悬索桥施工中鞍座顶推的研究[J]. 中国工程科学, 2010, 12(7): 68-73 DOI:

登录浏览全文

4963

注册一个新账户 忘记密码

参考文献

AI Summary AI Mindmap
PDF (723KB)

47

访问

0

被引

详细

导航
相关文章

AI思维导图

/