Assistant Pullback Technique for Main Span Closure of Sutong Bridge

Chen Ming1, Luo Chengbin1, Wu Qihe1,2, Zhang Yongtao1,2, You Xinpeng1,2

中国工程科学 ›› 2009, Vol. 11 ›› Issue (1) : 69 -75.

PDF (171KB)
中国工程科学 ›› 2009, Vol. 11 ›› Issue (1) : 69 -75.

Assistant Pullback Technique for Main Span Closure of Sutong Bridge

作者信息 +

Assistant pullback technique for main span closure of Sutong Bridge

Author information +
文章历史 +
PDF (175K)

摘要

Sutong bridge is a cable stayed bridge with a steel box girder and a main span of 1088m. The erection of upper structure adopts geometry control method and requires no change to the unit’s size and the structure’s none-stress geometry. Before main span closure, the cantilever of girder reaches 540.8m, the structure state is noticeably influenced by external circumstances, the main span closure face great difficulty. By abstracting the advantage of the pullback method abroad and the domestic temperature-cutting method, a new assistant pullback method have put forward and bring into practice actually. In this paper, the analysis key point of practice conditions、key parameter of practice、main measures of the method, and the performance is introduced.

Abstract

Sutong Bridge is a cablestayed steel box girder bridge with a main span of 1 088 m. The erection of upper structure adopts geometry control method and requires no change to the unit’s size and the structure’s nonestress geometry. Before main span closure, the cantilever of girder reaches 540.8 m, the structure state is noticeably influenced by external circumstances, the main span closure face great difficulty. By abstracting the advantage of the pullback method abroad and the domestic temperaturecutting method, a new assistant pullback method have put forward and bring into practice actually. In this paper, the analysis key point of practice conditions, key parameter of practice, main measures of the method and the performance is introduced.

关键词

Sutong Bridge / Assistant Pullback / Main Span Closure / Geometric control methord / Construction technology

Key words

Sutong Bridge / assistant pullback / main span closure / geometric control methord / construction technology

引用本文

引用格式 ▾
Chen Ming1, Luo Chengbin1, Wu Qihe1,2, Zhang Yongtao1,2, You Xinpeng1,2 Assistant Pullback Technique for Main Span Closure of Sutong Bridge[J]. 中国工程科学, 2009, 11(1): 69-75 DOI:

登录浏览全文

4963

注册一个新账户 忘记密码

参考文献

AI Summary AI Mindmap
PDF (171KB)

27

访问

0

被引

详细

导航
相关文章

AI思维导图

/