Key technologic problems on underwater shield tunnel

Author information +
文章历史 +
PDF (673K)

摘要

结合武汉长江隧道等水下盾构隧道工程,对水下盾构施工合理覆盖层厚度、盾构类型及关键参数确定进行了分析。对水下盾构施工关键技术如开挖面稳定技术、预防泥水喷发技术、防止隧道上浮技术、盾构姿态控制技术、长距离掘进及盾构水中对接技术、盾构始发与到达技术等进行了归纳。

Abstract

Combined with some underwater shield tunnels such as Wuhan Changjiang tunnel, the determination of reasonable cover thickness, the shield type and key parameter selection are analyzed. The key technology of stabilizing working face, preventing muddy water eruption, preventing tunnel floating, controlling shield direction, excavating long distance, abutting joint underwater, shield launching and arriving are generalized.

关键词

水下隧道 / 盾构法 / 覆盖层厚度 / 盾构选型 / 关键技术

Key words

underwater tunnel / shield / cover thickness / type selection / key construction technology

Author summay

孙谋(1971-),男,河南新乡市人,中铁隧道局高级工程师,北京交通大学博士研究生,研究方向为隧道及地下工程

引用本文

引用格式 ▾
孙谋,谭忠盛 盾构法修建水下隧道的关键技术问题[J]. 中国工程科学, 2009, 11(7): 18-23 DOI:

登录浏览全文

4963

注册一个新账户 忘记密码

参考文献

AI Summary AI Mindmap
PDF (659KB)

1252

访问

0

被引

详细

导航
相关文章

AI思维导图

/