摘要

论述了秦山二期核电工程主要的自主创新内容,包括新的堆芯设计,为此进行的试验研究和计算分析,以及为新堆所作的流致振动试验、分析和堆上实测;针对二环路的安全系统的改进及相应的安全分析,以提高其安全冗余度;根据二环路的特点对核电站的参数及其配套的设备设计进行了优化,使得核电站的出力达到最大;主厂房和常规岛厂房根据二环路及厂址的特点进行了创新。自主研制了控制棒驱动机构和装卸料机,其性能超出了设计指标;采取多种方法式使大部分主设备实施国产化。在土建安装上实施了穹顶整体吊装。在调试方面实施了汽轮发电机组的非核蒸汽冲转

关键词

核能工程 ; 二期

图片

图 1

参考文献

[ 1 ] Ye Qizhen. Design and construction of Qinshan 600 MW NPP[A]. Construction Experiment Collection of Qinshan NPP Phase Ⅱ[C]. Beijing: Atomic Energy Publishing Company, 2004. 25~ 36

[ 2 ] Yang Lanhe, et al. Organization and management for production preption of Qinshan second NPP[A]. Construction Experiment Collection of Qinshan NPP Phase [C]. Beijing: Atomic Energy Publishing Co Ⅱ mpany, 2004. 57~75

[ 3 ] Yu Zhongde. Specialty and meaning of self-reliance commissioning of Qinshan nuclear power units phase Ⅱ[A]. Construction Experiment Collection of Qinshan NPP Phase Ⅱ[C]. Beijing: Atomic Energy Publishing Company, 2004.52~56

[ 4 ] Zhang Zongyao, et al. The reactor core design of Qinshan nuclear power project phase Ⅱ[A]. Construction Experiment Collection of Qinshan NPP Phase Ⅱ[C]. Beijing: Atomic Energy Publishing Company, 2004. 3~12

[ 5 ] Zong Guifang, et al. 600 MW reactor hydraulic model experimental investigation of Qinshan nuclear power project phase Ⅱ[A]. Construction Experiment Collection of Qinshan NPP Phase Ⅱ[C]. Beijing: Atomic Energy Publishing Company, 2004. 51~56

[ 6 ] Wu Zhenglin, Zhang Jingcai. General evaluation of reactor internal fluid-induced vibration of Qinshan 600 MW NPP phase Ⅱ[A]. Construction Experiment Collection of Qinshan NPP Phase Ⅱ[C]. Beijing: Atomic Energy Publishing Company, 2004. 82~93

[ 7 ] Ma Jianzhong, Yang Yilun. Reactor barrel fluid-induced vibration response calculation of 600 MW NPP[A]. Construction Experime nt Collection of Qinshan NPP Phase Ⅱ[C]. Beijing: Atomic Ener gy Publishing Company, 2004. 71~76

[ 8 ] Jing Chunning, Liu Hong. Specialty and improvement of engineering safety features of Qinshan nuclear power project phase Ⅱ[A]. Construction Experiment Collection of Qinshan NPP Phase Ⅱ[C]. Beijing: Atomic Energy Publishing Company, 2004. 116~119

[ 9 ] Chen Mao. Containment design technology of Qinshan nuclear power project phase Ⅱ[A]. Construction Experiment Collection of Qinshan NPP Phase Ⅱ[C]. Beijing: Atomic Energy Publishing Company, 2004. 287~291

[10] Li Chengde. Design specialty of conveI Li cheng deⅡ[A]. Construction Experiment Collection of Qinshan NPP Phase Ⅱ[C]. Beijing: Atomic Energy Publishing Company, 2004. 377~378

[11] Li Hongying. CRDM design of Qinshan nuclear power project phase Ⅱ[A]. Construction Experiment Collection of Qinshan NPP Phase Ⅱ[C]. Beijing: Atomic Energy Publishing Company, 2004. 418~423

[12] Tang Xinhuang. Refueling machineⅡ[A]. Construction Experiment Collection of Qinshan NPP Phase Ⅱ[C]. Beijing: Atomic Energy Publishing Company, 2004. 693~698

相关研究