结合所承担的铁道部及中铁建总公司科研课题“客运专线铁路简支箱梁梁场工业化研究”的研究成果,及近30个梁场的规划设计实践,对梁场选址、梁场的平面布置及设备配套等梁场建设的3大重要内容进行了全面深入的论述。
On the basis of the research results of the project, the Research on the Industrialization of Freely Supported Box and Girder for Passenger Express Line, in Ministry of Railways and China Railway Construction Corporation, and the programming and design experience for almost 30 girder prefabrication fields, the three important aspects of girder field construction, i.e. site election, plane layout and corollary equipment, are discussed in depth.
passenger express line / girder field / site selection / plane layout / corollary equipment
/
〈 |
|
〉 |