Sutong bridge is a cable stayed bridge with a steel box girder and a main span of 1088m. The erection of upper structure adopts geometry control method and requires no change to the unit’s size and the structure’s none-stress geometry. Before main span closure, the cantilever of girder reaches 540.8m, the structure state is noticeably influenced by external circumstances, the main span closure face great difficulty. By abstracting the advantage of the pullback method abroad and the domestic temperature-cutting method, a new assistant pullback method have put forward and bring into practice actually. In this paper, the analysis key point of practice conditions、key parameter of practice、main measures of the method, and the performance is introduced.
Abstract
Sutong Bridge is a cablestayed steel box girder bridge with a main span of 1 088 m. The erection of upper structure adopts geometry control method and requires no change to the unit’s size and the structure’s nonestress geometry. Before main span closure, the cantilever of girder reaches 540.8 m, the structure state is noticeably influenced by external circumstances, the main span closure face great difficulty. By abstracting the advantage of the pullback method abroad and the domestic temperaturecutting method, a new assistant pullback method have put forward and bring into practice actually. In this paper, the analysis key point of practice conditions, key parameter of practice, main measures of the method and the performance is introduced.
关键词
Sutong Bridge /
Assistant Pullback /
Main Span Closure /
Geometric control methord /
Construction technology
Keywords
Sutong Bridge /
assistant pullback /
main span closure /
geometric control methord /
construction technology
Chen Ming1, Luo Chengbin1, Wu Qihe1,2, Zhang Yongtao1,2, You Xinpeng1,2.
Assistant Pullback Technique for Main Span Closure of Sutong Bridge. 中国工程科学. 2009, 11(1): 69-75