工程网络计划的LR型模糊系数线性规划方法

  • 高朋、冯俊文()

作者信息 +

Linear programming method with LR type fuzzy numbersfor network scheduling

  • Gao Peng、Feng Junwen

Author information +
History +

摘要

工程网络计划的基础是对各工序持续时间的估计,而导致工序工期不确定性的因素不仅具有随机性,通常也具有模糊性。文章提出一种具有LR型模糊数的线性规划模型,解决了工程网络计划的时间参数 估计和关键路径识别问题,并通过引入λ截集来充分描述决策者在不同情形下对工序工期估计的可信程度。 最后给出一实例详细说明了该方法的应用过程及有效性。

Abstract

Estimation of activity duration is a basic problem for project scheduling. However, the uncertainty of activity duration originates from both probability and fuzziness in the real world. This paper develops a linear programming method with LR type fuzzy numbers, which aims to estimate activity duration and identify critical path, and applies the λ - cut to indicate the degree of optimism of a decision maker. Finally, an example is given to demonstrate the application and validity of the proposed method.

关键词

工程网络计划 / 模糊线性规划 / 工序

Keywords

network scheduling / fuzzy linear programming / activity

引用本文

导出引用
高朋,冯俊文. 工程网络计划的LR型模糊系数线性规划方法. 中国工程科学. 2009, 11(2): 70-74

参考文献

基金
“八六三”高技术研究和发展计划资助项目(2007 KX301) ;江苏科协重大软科学资助项目( RS06108)
PDF(736 KB)

Accesses

Citation

Detail

段落导航
相关文章

/