悬索桥施工中鞍座顶推的研究

齐东春()1、王昌将2、沈锐利1、林恰1

中国工程科学 ›› 2010, Vol. 12 ›› Issue (7) : 68-73.

PDF(723 KB)
PDF(723 KB)
中国工程科学 ›› 2010, Vol. 12 ›› Issue (7) : 68-73.

悬索桥施工中鞍座顶推的研究

  • 齐东春()1、王昌将2、沈锐利1、林恰1

作者信息 +

Saddle pushing analysis in suspension bridge construction

  • Qi Dongchun1、Wang Changjiang2、Shen Ruli1、Lin Qia1

Author information +
History +

摘要

对悬索桥鞍座顶推中预偏量计算控制原则、塔顶位移与塔底应力的关系、顶推量和顶推时间的确定等几个问题进行了探讨,阐明了鞍座平衡条件的合理模式及预偏量的计算方法。结合坝陵河大桥鞍座的顶推计算分析,得出超量顶推可增加顶推时间间隔,减少顶推次数,顶推后的工况是主缆抗滑移验算的不利工况等结论。

Abstract

Some problems existing in saddle pushing, such as the pre-displacement control principle, the relation of tower top displacement and tower bottom stress, the method of determining saddle pushing stages and pushing values, are discussed. The reasonable model of saddle equilibrium condition and the pre-displacement calculation method are expounded. Combining with saddle pushing analysis of Baling River Bridge, the conclusion that the excess pushing scheme can increase the interval of each pushing and reduce pushing times is obtained. The cases following saddle pushing are the unfavorable conditions for main cables anti-sliding checking.

关键词

悬索桥 / 鞍座顶推 / 鞍座平衡条件 / 塔顶偏位 / 塔底应力

Keywords

suspension bridge / saddle pushing / saddle equilibrium condition / tower top displacement / tower bottom stress