医院中子照射器试运行
Test operation of in-hospital neutron irradiator
Li Yiguo1,2、Peng Dan1、Zou Shuyun1、Wu Xiaobo1、Zhang Jinhua1、Zhang Zizhu1、Xia Pu1、Zou Xiaoyan2、Liu Tong2、Zhou Yongmao3
医院中子照射器及其辅助系统于2010年年初完成热调试试验,随后投入试运行至今,共开堆99次(天),累积释放能量1 832.42 kW·h (折合积分中子注量为2.198 9×1017 cm-2)。试运行期间实验数据显示,医院中子照射器及其辅助系统满足规定的运行限值和条件,未发生任何事故,具有很好的安全性与可靠性,达到了设计要求。
In 2010, the commissioning of in-hospital neutron irradiator (IHNI) and its systems were completed. The operation with power started since then. The IHNI has operated by 99 times. The release of total energy is 1 832.42 kW·h with the corresponding integral neutron flux of 2.198 9×1017 cm-2. The test operation data shows that the operation values of IHNI and its relevant systems are smaller than the limited value, which manifests that IHNI is safe and reliable.
in-hospital neutron irradiator (IHNI) / test operation / limited value and condition
/
〈 |
|
〉 |