三峡升船机船厢室段混凝土浇筑设备布置研究
Research on concreting equipment planning of ship lift boat cab segment in Three Gorges Project
Huang Jiaquan、Ma Shaofu、Yu Yongjun
本文详细介绍了三峡升船机船厢室段混凝土施工设备的选型过程,包括船厢室段混凝土施工特性分析,投标阶段浇筑设备选型论证,施工阶段对设备选型的系统调整和优化。施工设备的工程实践效果表明,三峡升船机船厢室段混凝土浇筑设备布置方案有效覆盖了所有浇筑面,满足浇筑高峰期混凝土入仓强度的要求,施工进度、成本、安全均得到有效控制。三峡升船机船厢室段混凝土浇筑设备经过前期的合理规划,以及后期的系统调整与优化,对三峡升船机工程的顺利完建发挥了重要作用,具有较高的推广应用价值。
This paper describes the selection process on concrete construction equipment of ship lift boat cab segment in Three Gorges Project in detail, including analysis on the characteristics of concrete construction in boat cab segment, selection argumentation of construction equipment at the tender stage and system adjustment and optimization of equipment selection at the construction stage. The engineering practice effect of construction equipment indicates that the concrete pouring equipment layout plan for Three Gorges Project ship lift boat cab section effectively covers all pouring surface, meeting the warehousing strength requirements in concrete pouring peak, and the construction schedule, cost, safety, can be effectively controlled. The concreting equipments of Three Gorges Project ship lift boat cab segment have been pre-rational planned, post-system adjusted and optimizated , they play an important role in the successful end of construction of Three Gorges ship lift project, and they have high promotion and application value.
施工设备 / 设备布置 / 混凝土浇筑 / 船厢室 / 三峡升船机
construction equipment / equipment layout / concrete pouring / boat cab / Three Gorges Project ship lift
/
〈 |
|
〉 |