Feasibility Study on Design and Construction of Concrete Filled Steel Tubular Arch Bridge with a Span of 700m
Zheng Jielian,Wang Jianjun,Mou Tingmin,Feng Zhi,Han Yu,Qin Dayan
Strategic Study of CAE ›› 2014, Vol. 16 ›› Issue (8) : 33 -37.
Feasibility Study on Design and Construction of Concrete Filled Steel Tubular Arch Bridge with a Span of 700m
Based on the design and complete construction techniques of 500m-span concrete filled steel tubular (CFST) arch bridge, a feasibility study on design and construction techniques of 700m-span CFST arch bridge was conducted. The general design and construction schemes were figured out, and key techniques were detailed studied such as manufactory and installation of arch ribs, concrete grouting in tube, etc.. The results showed that there are no technical hurdles to build 700m-span CFST arch bridges. Considering economical efficiency, safety and other factors, CFST arch bridge is a strong competitor when building a 700m-span bridge and should be put on engineering practice and spread as soon as possible.
bridge engineering / span of 700m grade / concrete filled steel tubular(CFST) arch bridge / design / construction
/
〈 |
|
〉 |