Clearance grouting process test of Three Gorges Project ship lift rack and nut column

Zhan Jianxia and Li Jihu

Strategic Study of CAE ›› 2013, Vol. 15 ›› Issue (9) : 45 -49.

PDF (914KB)
Strategic Study of CAE ›› 2013, Vol. 15 ›› Issue (9) : 45 -49.

Clearance grouting process test of Three Gorges Project ship lift rack and nut column

Author information +
History +
PDF (914KB)

Abstract

In order to choose the suitable grouting material and grouting process, and simulate the actual situation of clearance grouting of rack and nut column in ship lift, grouting process test and prototype grouting experiment were carried out respectively. Comparing three kinds of domestic grouting material and the German PAGEL grouting material in grouting process test, the experimental results showed that the physical and mechanical property indexes of German PAGEL grouting material were superior to the domestic grouting material. In prototype grouting test, selection of the grouting equipment type, mixing time, templates seal, method of grouting parameters control of grouting flow were researched, and some applicable grouting material and grouting process were selected which were suitable for the rack and nut column joint in Three Gorges Project ship lift. The above test effects were obvious, and solved the construction problems of great difficulty in grouting seal and easy blockage of pipeline, etc.

Keywords

rack / nut column / grouting / ship lift / Three Gorges Project

Cite this article

Download citation ▾
Zhan Jianxia and Li Jihu. Clearance grouting process test of Three Gorges Project ship lift rack and nut column. Strategic Study of CAE, 2013, 15(9): 45-49 DOI:

登录浏览全文

4963

注册一个新账户 忘记密码

References

AI Summary AI Mindmap
PDF (914KB)

254

Accesses

0

Citation

Detail

Sections
Recommended

AI思维导图

/