Aiming at the success of the franchise of Nanjing Cioss-River Tunnel, this paper analysis the structure of the risks in the infrastructure franchise and its influences. For it is impossible to get a complete contract between the private sector and the government, the goverment should take some appropriate measures and set up a good governance structure to deal with these risks, which is a key factor to affect the success of franchise.