Linear programming method with LR type fuzzy numbersfor network scheduling
Gao Peng、Feng Junwen
Strategic Study of CAE ›› 2009, Vol. 11 ›› Issue (2) : 70-74.
Linear programming method with LR type fuzzy numbersfor network scheduling
Gao Peng、Feng Junwen
Estimation of activity duration is a basic problem for project scheduling. However, the uncertainty of activity duration originates from both probability and fuzziness in the real world. This paper develops a linear programming method with LR type fuzzy numbers, which aims to estimate activity duration and identify critical path, and applies the λ - cut to indicate the degree of optimism of a decision maker. Finally, an example is given to demonstrate the application and validity of the proposed method.
network scheduling / fuzzy linear programming / activity
/
〈 |
|
〉 |