Construction risk estimation of TBM and discussion on key risk countermeasures of Bohai Strait tunnel

Li Da1、Hong Kairong2、Tan Zhongsheng3

Strategic Study of CAE ›› 2013, Vol. 15 ›› Issue (12) : 95-100.

PDF(1843 KB)
PDF(1843 KB)
Strategic Study of CAE ›› 2013, Vol. 15 ›› Issue (12) : 95-100.

Construction risk estimation of TBM and discussion on key risk countermeasures of Bohai Strait tunnel

  • Li Da1、Hong Kairong2、Tan Zhongsheng3

Author information +
History +

Abstract

The identification and estimation of construction risks of Bohai Strait tunnel are made by means of analytic hierarchy process (AHP) fuzzy comprehensive evaluation method, with the construction risks estimation of existing devised program of Bohai Strait tunnel as an example. The results show that the construction risk grade of Bohai Strait tunnel is grade Ⅲ. The key construction risks of Bohai Strait tunnel, including manufacturing of main bearing of tunnel boring machine (TBM), mud/water bursting and ventilation,are analyzed, and the countermeasures and problems to be solved are presented. The paper can provide reference for the construction program determination of Bohai Strait tunnel and for the planning,design and construction program of sea-crossing tunnels in the future.

Keywords

Bohai Strait tunnel / analytic hierarchy process / fuzzy evaluation / risk estimation / risk countermeasure

Cite this article

Download citation ▾
Li Da,Hong Kairong and Tan Zhongsheng. Construction risk estimation of TBM and discussion on key risk countermeasures of Bohai Strait tunnel. Strategic Study of CAE, 2013, 15(12): 95‒100
AI Summary AI Mindmap
PDF(1843 KB)

Accesses

Citations

Detail

Sections
Recommended

/