Research on concreting equipment planning of ship lift boat cab segment in Three Gorges Project

Huang Jiaquan、Ma Shaofu、Yu Yongjun

Strategic Study of CAE ›› 2013, Vol. 15 ›› Issue (9) : 59-63.

PDF(1282 KB)
PDF(1282 KB)
Strategic Study of CAE ›› 2013, Vol. 15 ›› Issue (9) : 59-63.

Research on concreting equipment planning of ship lift boat cab segment in Three Gorges Project

  • Huang Jiaquan、Ma Shaofu、Yu Yongjun

Author information +
History +

Abstract

This paper describes the selection process on concrete construction equipment of ship lift boat cab segment in Three Gorges Project in detail, including analysis on the characteristics of concrete construction in boat cab segment, selection argumentation of construction equipment at the tender stage and system adjustment and optimization of equipment selection at the construction stage. The engineering practice effect of construction equipment indicates that the concrete pouring equipment layout plan for Three Gorges Project ship lift boat cab section effectively covers all pouring surface, meeting the warehousing strength requirements in concrete pouring peak, and the construction schedule, cost, safety, can be effectively controlled. The concreting equipments of Three Gorges Project ship lift boat cab segment have been pre-rational planned, post-system adjusted and optimizated , they play an important role in the successful end of construction of Three Gorges ship lift project, and they have high promotion and application value.

Keywords

construction equipment / equipment layout / concrete pouring / boat cab / Three Gorges Project ship lift

Cite this article

Download citation ▾
Huang Jiaquan,Ma Shaofu,Yu Yongjun. Research on concreting equipment planning of ship lift boat cab segment in Three Gorges Project. Strategic Study of CAE, 2013, 15(9): 59‒63
AI Summary AI Mindmap
PDF(1282 KB)

Accesses

Citations

Detail

Sections
Recommended

/