The discussion on the settlement of the high speed railway track led by non-engineering factor and its countermeasure

Engineering Management Center of China Railway Corporation,Beijing 100844,China

Received: 2012-11-29 Available online: 2014-01-22 13:11:20.000

Next Previous

Abstract

Combined with the cases of the track settlement led by non- engineering factor,the paper analyzed the reason and its hazard to the high speed railway track which are over the design and code standard,then concluded the correlation question type and gave out the suggestion and opinion,hoping to help solve the similar questions.

Figures

图1

图2

图3

图4

References

[ 1 ] 铁道第三勘察设计院集团有限公司,中铁第四勘察设计院集 团有限公司,中国铁道科学研究院. TB 10621—2009 高速铁路 设计规范(试行)[S]. 北京:中国铁道出版社,2010.

[ 2 ] 中铁四局集团有限公司. 铁建设[2010]241号 高速铁路路基工 程施工技术指南[S]. 北京:中国铁道出版社,2011.

[ 3 ] 中铁十二局集团有限公司. TB 10751—2010 高速铁路路基工 程施工质量验收标准[S]. 北京:中国铁道出版社,2011.

[ 4 ] 铁道科学研究院. 铁建设[2006]158号 客运专线铁路无碴轨道 铺设条件评估技术指南[S]. 北京:中国铁道出版社,2006.

[ 5 ] 尤昌龙. 关于对京沪高速铁路路基有关问题的思考[J]. 铁道工 程学报,2001,9(3):18-20,23. link1

[ 6 ] 中国新闻网. 地层下陷超预期 台湾高铁提早9年加固桥梁[EB/ OL]. [2011- 04- 11]. http://www.chinanews.com/tw/2011/04- 11/ 2962756.shtml.

[ 7 ] 中国新闻网. 台湾高铁沉降路段三处得到改善 一处继续恶化 [EB/OL].[2012- 04- 06]. http://www.chinanews.com/tw/2012/04- 06/3799742.shtml. link1

Related Research