Journal Home Online First Current Issue Archive For Authors Journal Information 中文版

Strategic Study of CAE >> 2013, Volume 15, Issue 9

Construction procedure study of ship chamber of Three Gorges Project ship lift

China Gezhouba Group Co., Ltd. Three Gorges Company, Yichang, Hubei 443002, China

Received: 2013-06-20 Available online: 2013-09-10 13:14:10.000

Next Previous

Abstract

Aiming at the impact of load imposed order of balance weight and ship compartments on the the deformation of pillar and built-in structure parts, the construction order of ship compartments chamber and equipment installation sequence scheme are studied, which Solved the technical problems that the impact of load imposed order of balance weight and ship compartments on the the deformation of nut column, rack ,and vertical direction displacement. According to the simulation results of pillar structure, the impact of the ship chamber and balance weight loading sequence to the nut, rack and vertical guide displacement in the direction across the river, along the river and vertical is analyzed. Reasonable ship lift ship compartments chamber construction procedure and construction schedule arrangement are set by optimizing the construction procedures. The construction procedures can make nut, rack, vertical direction, the structure of the ship compartments and pillar under various operating conditions on the displacement meet the safety requirements. And the procedures based on the construction progress of the construction can meet the requirements of ship lift commissioning. Engineering practice proved that chamber construction procedures of Three Gorges Project lift ship established in this paper are reasonable and scientific which ensure the smooth construction of ship chamber of Three Gorges Project lift ship and guarantee the safe operation of ship lift. these construction procedures can provide a reference for similiar project.

Figures

图1

图2

图3

图4

图5

图6

图7

图8

图9

References

[ 1 ] 朱 虹,邓润兴. 三峡升船机总体布置设计[J]. 人民长江,2009, 40(27):48-50. link1

[ 2 ] 中国水利水电科学研究院. 长江三峡水利枢纽升船机安全可靠 性评估报告(第一分册)[R]. 2007.

[ 3 ] 长江勘测设计研究院,中国水利水电科学研究院,长江科学院. 三 峡升船机塔柱施工仿真研究与结构计算分析工作大纲[R]. 2007.

[ 4 ] 中国水利水电科学研究院. 三峡升船机塔柱结构施工全过程仿 真分析研究(中间成果)[R]. 2008.

Related Research