This paper describes the embodiment of concrete construction supporting system of the Three Gorges Project ship lift tower beams. It begins with the load requirements, structural strength requirements, and deformation stability requirements of the Bailey rack supporting system. Through scientific computing, reasonable bearing system design, structural design and the upper steel pipe bent design of Bailey rack supporting system are developed. And the monitoring of the stress and strain, deformation, displacement are done to the Bailey rack supporting system and the corresponding tower concrete wall structure around the concrete pouring process. The monitoring results show that the beam supporting system meets the pouring and supporting requirements of beams. The construction quality is first-rate, safety and reliable. Both the design and the construction are feasible.

Figures

图1

图2

图3

图4

图5

图6

图7

图8

图9

图10

References

[ 1 ] 中华人民共和国建设部,中华人民共和国国家质量监督检验 检疫总局. GB 50017—2003 钢结构设计规范[S]. 北京:中国计 划出版社,2003.

[ 2 ] 中华人民共和国交通部. JTG/T F50—2011 公路桥涵施工技术 规范[S]. 北京:人民交通出版社,2011.

[ 3 ] 中华人民共和国国家经济贸易委员会. DL/T 5110—2000 水电 水利工程模板施工规范[S]. 北京:中国电力出版社,2001.

[ 4 ] 中华人民共和国住房和城乡建设部. JGJ 130—2011建筑施工 扣件式钢管脚手架安全技术规范[S]. 北京:中国建筑工业出版 社,2011.

Related Research