Research and application of aerial comprehensive lifting platform of tower column of Three Gorges Project ship lift
China Gezhouba Group Co.,Ltd. Three Gorges Company,Yichang,Hubei 443002,China
Next Previous
Abstract
The overall construction program has been changed in the extension project of Three Gorges Project ship lift. Because of it, the tower column, rack, nut post, counterweight, and longitudinal guide rail should be constructed at the same time which forms the grade separation operation. In this case, conventional shelving scheme can not meet the requirement of construction. So the aerial comprehensive lifting platform is adopted which can quickly change the vertical construction site and meet the requirements of different parts and working procedures. This platform contains hoist lifting platform, gear-rack lifting platform, and hanging lifting platform. Comprehensive lifting platform can meet the requirements of the installation of metal structure, construction of second stage concrete, installation of mechanical and electrical equipment, concrete pouring of second stage concrete, and pagel grouting. It can relief the intense construction period. This technique after design can be popularized and applied in similar project.
Keywords
Three Gorges Project ship lift ; construcion of tower column ; aerial work ; comprehensive lifting platform ; construction technique
References
[ 1 ] 梁仁强. 关于调整施工程序 [J]. 中国三峡建设年鉴,2011,150.
[ 2 ] 张俊松. 三峡升船机齿条、螺母柱一期埋件安装[J]. 价值工程, 2011,31(30):41-43. link1