Construction technology of Three Gorges Project ship lift hydraulic self-climbing formwork

Engineering Research Institute, China Energy construction Group Co. Ltd., Beijing 100029, China

Received: 2013-06-27 Available online: 2013-09-10 13:09:01.000

Next Previous

Abstract

The construction time limits for the tower column concrete of Three Gorges Project ship lift is pressed for time and require high accuracy. In order to ensure the construction progress and quality, the hydraulic self-climbing formwork is used. This paper focuses on the construction technology of hydraulic self-climbing formwork, improvement measures of self-climbing formwork as well as structural measures made in the plate girders and corbels department of tower to meet the rising-up of self-climbing formwork on Three Gorges Project ship lift tower column concrete. It has been found that application and improvement of the hydraulic self-climbing formwork construction technology meet the design requirements of the tower column cylinder concrete of the Three Gorges ship lift, effectively improve the construction efficiency, save cost, ensure the engineering quality and improve the safety of the construction,can provide reference for other hydropower project construction.

Figures

图1

图2

图3

图4

图5

图6

图7

References

[ 1 ] 孙精石,周兴华,赵德志,等. 关于升船机的调查研究[J].水道港 口,2001,22(3):141-145. link1

[ 2 ] 朱 虹,邓润兴. 三峡升船机总体布置设计[J].人民长江,2009, 40(27):48-50. link1

[ 3 ] 梁仁强,李 锋. 三峡升船机施工技术研究与实践[J].人民长 江,2011,42(16):51-55. link1

[ 4 ] 张良杰. 高层建筑液压爬升模板[C]//施工企业模板与脚手架应 用技术交流会论文集,2007. link1

Related Research