Journal Home Online First Current Issue Archive For Authors Journal Information 中文版

Strategic Study of CAE >> 2002, Volume 4, Issue 7

Analysis for the Stability of Covered Karst Base and a Pre-disposing Way with Pressure Grouting

1. Department of Civil Engineering, Guangxi Institute of Technology, Liuzhou, Guangxi 545005, China

2. Department of Civil Engineering, Jianghan Institute of Petroleum, Jingzhou, Hubei 434102, China

3. The First Survey and Design Institute of the Ministry of Railways, Lanzhou 730080, China

4. College of Civil Engineering and Architecture, Wuhan University of Science and Technology, Wuhan 430070, China

Received: 2001-11-12 Revised: 2002-01-16 Available online: 2002-07-20

Next Previous

Abstract

By analysis on the stability of covered karst base, a kind of way, which can be adopted to predispose the covered karst base using pressure grouting, is developed in this paper. The evaluation of grouting effect indicates this way can be carried out economically and technically.

Figures

图1

References

[ 1 ] 岩土工程手册编写委员会.岩土工程手册[M ].北京:中国建筑工业出版社, 1994

Related Research