Journal Home Online First Current Issue Archive For Authors Journal Information 中文版

Strategic Study of CAE >> 2003, Volume 5, Issue 7

Science and Technology Innovation of the Deep Water High Earth-rock Cofferdam in the Three Gorges Project

China Yangtze Three Gorges Project Development Corporation , Yichang , Hubei 443002, China

Received: 2003-01-27 Available online: 2003-07-20

Next Previous

Abstract

The deep water high earth-rock cofferdam in the 2nd phase construction of TGP is a hard and challenge project, whose degree of difficulty in the technological problems is much harder than that of the similar projects. During the period from 1998 to 2002, the cofferdam protected the construction pit of the left-bank dam and powerhouse, stood the test of the heavy flood in 1998, and made the 2nd stage construction completed smoothly. The quality of the cofferdam is good, and it fulfilled the historical tasks satisfactorily. The article introduced the whole course of the systematical research through the aspects of the experimental research, the design and construction, the organization and management, the safety monitor and the cofferdam demolition etc.

Figures

图1

References

[ 1 ] 中国长江三峡工程开发总公司,等.三峡工程深水高土石围堰的研究与实施[R].2002.358一359

[ 2 ] 潘家峥.对二期围堰的评价[J].中国三峡建设,1999.(5)1~3

[ 3 ] 王家柱.二期横向围堰工程几个主要技术问题[J].中国三峡建设,1999,(5):4~7

Related Research