Unstressed state control method for process control of structure formed by stages

China Railway Major Bridge Engineering Group Co., Ltd., Wuhan 430050, China

Received: 2009-08-13 Revised: 2009-08-23 Available online: 2009-10-12 14:00:17.000

Next Previous

Abstract

This paper establishes a mechanical equilibrium equation for structure in any construction process of bridge formed by stages, and thus concludes that the core of process control for stage-constructed bridge is the quantity of unstressed state of structural elements. The control and adjustment of quantity of unstressed state of the structural elements provides a solution to the problem of rection calculation for bridge constructed by stages. Based on the principle that internal force and displacement have nothing to do with the construction process on the premise of a constant quantity of unstressed state, parallel operation of multiple working procedures can be put into practice, and the automatic filtration of influences from temporary load and temperature during construction can be therefore well realized.

Figures

图1

图2

图3

图4

图5

图6

图7

图8

References

[ 1 ] 中铁大桥勘测设计院有限公司.分阶段施工桥梁的无应力状态控制法与工程实践[R].湖北,2007

[ 2 ] 秦顺全.分阶段施工桥梁的无应力状态法控制法[J].桥梁建设,2008,(1):8-14 link1

[ 3 ] 奥登JT,里帕格EA.弹性结构力学[M].北京:中国建筑工业出版社,1986

[ 4 ] 秦顺全.桥梁施工控制———无应力状态法理论与实践[M].北京:人民交通出版社,2006

[ 5 ] 秦顺全,林国雄.斜拉桥安装计算———倒拆法与无应力状态控制法评述[A].1992年全国桥梁结构学术大会论文集[C].上海:同济大学出版社,1992:569-573

[ 6 ] 黄晓航.夷陵长江大桥三塔斜拉桥施工监控[J].桥梁建设,2003,(3):22-24 link1

[ 7 ] 秦顺全,谢红兵,刘孝军.武汉长江二桥斜拉桥安装计算及监控管理[J].桥梁建设,1995,(3):41-43 link1

[ 8 ] 黄晓航.武汉白沙洲大桥斜拉桥施工监控[A].中国公路学会桥梁和结构工程学会2000年桥梁学术讨论会论文集[C].北京:人民交通出版社,2000:409-412

[ 9 ] 秦顺全.斜拉桥安装无应力状态控制法[J].桥梁建设,2003,(2):31-34 link1

[10] 高宝峰,黄燕庆.天津塘沽区海河大桥施工监控[J].人民长江,2003,(6):59-60

[11] 吴运宏.重庆李渡长江大桥施工监控计算[J].桥梁建设,2006,(增刊2):180-182

Related Research