Development of network schedule standardization system in hydraulic and hydropower engineering

1. State Key Laboratory of Hydraulic Engineering Simulation and Safety, Tianjin University, Tianjin 300072, China;

2. HydroChina Kunming Engineering Corporation, Kunming 650051, China

Received: 2013-03-11 Available online: 2015-01-13

Next Previous

Abstract

Network schedule is an important part in construction organization and design in hydraulic and hydropower engineering. As most network schedule software provided limited functionality in schedule generation and analysis, leading to network schedule generation is time-consuming, laborious, inefficient, and low degree of standardization. Based on analysis of connotation of network standardization in hydraulic and hydropower engineering, this paper discussed the basic content of the network schedule standardization, developed the standardization system of network schedule in hydraulic and hydropower engineering, and introduced functions as network schedule aided generation, analysis, evaluation and review, as well as the output of results in detail. The system interface is friendly and intuitive visualization, and provides powerful computing and optimization capabilities, greatly improving the efficiency and quality of the preparation of the network schedule to engineering staffs, and provides a new way and means in quickly generating, analyzing and optimizing the network schedule.

Figures

图1

图2

图3

图4

图5

图6

图7

References

[ 1 ] Chris Hendrickson,Carlos Zozaya-Gorostiza. Expert system for construction planning [J]. Journal of Computing in Civil Engineering,1987,1(4):253-269. link1

[ 2 ] Navlnchandra D,Sriram D. GHOST:Project network generator [J]. Journal of Computing in Civil Engineering,1988,2(3):239- 254. link1

[ 3 ] Jonathan Cherneff,Robert Logcher. Integrating cad with construction schedule generation [J]. Journal of Computing in Civil Engineering,1991,5(1):64-84. link1

[ 4 ] Martin Fisher,Florian Aalami,Michele O’Brien Evans. Modelbased constructability analysisz:The MOCA system [R]. California:Stanford University (CIFE),1994.

[ 5 ] Nicola J Chevallier,Alan D Russell. Automated schedule generation [J]. Canadian Journal of Civil Engineering,1998,25(6): 1059-1077. link1

[ 6 ] Nicola J Chevallier,Alan D Russell. Developing a draft schedule using templates and rules [J]. Journal of Construction Engineering and Management,2001,127(5):391-398. link1

[ 7 ] Dzeng R J,Wang W C,Tserng H P. Module-based construction schedule administration for public infrastructure agencies [J]. Journal of Construction Engineering and Management,2004,130 (1):5-14. link1

[ 8 ] Dzeng R J,Tserng H P,Wang W C. Automating schedule review for expressway construction [J]. Journal of Construction Engineering and Management,2005,131(1):127-136. link1

[ 9 ] Han- Guk Ryu,Hyun- Soo Lee,Moonseo Parkyu. Construction planning method using case- based reasoning(CONPLA- CBR) [J]. Journal of Computing in Civil Engineering,2007,21(6):410- 422. link1

[10] Chung-Wei Feng,Yi-Jao Chen. Using MD cad objects to automatically generate a contract- driven schedule [C]//2006 Proceedings of the 23rd International Symposium on Robotics and Automation in Construction. Japan:Tokyo,2006:740-745. link1

[11] Aleš Mrkela,Danijel Rebolj. Automated construction schedule creation using project information model [EB/OL]. 2010,http:// itc.scix.net/data/works/att/w78-2009-1-03.pdf. link1

[12] Laura Tupenaite,Loreta Kanapeckiene,Jurga Naimaviciene. Knowledge management model for construction projects [C]. Latvia:Riga,2008:313-320.

[13] Janusz Kulejewski. Planning of construction schedule with flexible constraints [C]//The 10th modern building materials,structures and techniques international conference. Lithuania:Vilnius,2010:442-445.

[14] Eva Mikulakova,Markus König,Eike Tauscher,et al. Knowledge- based schedule generation and evaluation [J]. Advanced Engineering Informatics,2010,24(4):389-403. link1

[15] 王仁超,郝伟峰. 工程项目中网络进度计划编制标准化研究 [J]. 价值工程,2012(11):71-72. link1

[16] 薄卫彪. 建设项目进度计划智能安排研究[D]. 上海:同济大 学,2006. link1